dongarandClaude Opus 5.5 ad2d090143 New projects from conversation (M2.5, PR B)
- propose_project(name, purpose, decisions) in a conversation goes up for
  a go-ahead (checked: a slug, not an existing project, no trailing
  question).
- On go, the provisioning checklist (D1): a repository with a README,
  protection on its default branch, the agent as a collaborator, a build
  VM, a deploy key, and the project entry as YAML with <...> to fill in.
- On "done", the agent reads its configuration again and adds the new
  project live (build_loop_agent(load=...); only additions), then checks
  what was provided (D4, verified, not assumed): permissions and
  protection as it sees them, then on a throwaway branch with an empty
  commit, a branch push must succeed and a push to the default branch and
  merging its own PR must be refused. The check's PR is closed and its
  branch deleted. Failures are said per item; nothing starts.
- Checked: the tracking issue (the distilled decisions, carrying the new
  item's ID), and the project's item, agreed and labelled `design`, whose
  first milestone is ARCHITECTURE.md and the build plan. A conversation
  waiting on provisioning doesn't close as idle.
- The walk replays exactly from its seed (item IDs too), and event IDs
  stay unique across simulated restarts, as a server's are.
- The test config holds output to 8192 tokens, under the test key's
  per-request cost cap.

Tests: new-project unit tests (checklist and its YAML parse as config, done
before the entry, what isn't set up, a checked project's record and first
PR, an existing name), protection enforced by a hook on the fake forge,
the walk proposing projects and saying done, and an e2e new project in a
repository the test operator provisions from the agent's checklist.

Co-Authored-By: Claude Opus 5.5 (1M context) <noreply@anthropic.com>
Claude-Session: https://claude.ai/code/session_01PPQ14L3LikyefCMFBqEbKE
2026-10-07 15:39:00 +00:00

22 KiB
Raw Blame History

Nisse — Development Plan

Status: agreed (PR #84); reworked in PR #92 after the architecture revision (PR #90). How to get from the code as it is to the architecture in docs/Architecture.md, in what order, and how each step is accepted. The architecture says what and why; this document says how and when, and is revised as work lands.

The priority is a minimal new loop, running live. Work is ordered to reach the smallest end-to-end version of the conversational loop (M2.1) as soon as possible; everything not needed for it waits. Each milestone is checked by an automated end-to-end test against real resources, not by hand.


1. Where we are

A survey of main (2026-10-02) against the architecture. Done means it exists and matches; partial, something exists but needs changing; none, not started.

Only nisse-dev has real code; nisse-core and nisse-ops are placeholders.

Section Status Notes
L1 Work model mostly done Work items with an active pointer (M1.1); issue intake (M2.1); queue, parking and blocked items (M2.2) on the new loop; no grace period yet
L2 Agent loop partial control.py, a fixed state machine with no-stranding, stop, abandon. Replaced by the new loop (Phase 2)
L3 Authority partial Revision binding and arrival stamping (gates.py); scope is still plan approval, not the issue and its conversation
L4 Classifier none
L5 Conversation partial Matrix transport, mentions, lenient commands; on the new loop, a thread per item, named and ambiguous commands, plain-language go-aheads (M2.3); little explanation
L6 Context partial Context fitting, per-role views and orchestrator facts (M1.2); no scope or agent memory
L7 Canonical log partial Work item and actor on every event, fact (M1.1, M1.2); no classifier_verdict, knowledge_retrieved
L8 Durability mostly done WAL store, intents, boot reconciliation, PR adoption, comment redelivery; to move onto the new loop
L9 Models and roles partial LiteLLM, delegation, ask_expert, eval capture; roles are still planner/executor, no capability profiles
L10 Knowledge vault none
L11 Injection partial Operator allowlists on every channel; no classifier
L12 Secrets, logging partial Structured state-change log; secrets in .env; no per-operation handout or redaction
L13 Execution none Tools run locally in the agent's process. The token leaks into the clone (#89)
D1–D2 Workflow partial On the new loop: issue intake, restatement and go-ahead (M2.1), labels (M2.3); no documents in the repo
D3–D4 Workspace, git partial Idempotent publishing; no fresh workspace (#62), git add -A (#80)
D5 Review partial PR conversation comments only (#69), watch stall (#70)
D7–D8 Deployment, projects partial Runs from a venv as a systemd unit on this box; project entries in config (M1.4); egress not enforced
O, X none No container image yet
specs/ done for now orchestrator.qnt (current loop), loop.qnt (the architecture, #91)

2. The environment today

  • Supporting services (X5): Matrix, Gitea, LiteLLM, Vaultwarden, LLDAP with Authelia. The infrastructure repository exists in Gitea.
  • Local inference: llama-swap on an RTX 4090 host (320 W cap). The benchmark (PR #55) chose qwen3.8-27b for local work.
  • Models by role today: executor qwen3.8-27b, planner and helper claude-opus-5-5, expert claude-haiku-4-5. Phase 2 moves to driver and helpers.
  • Bring-up runs on this development VM (scripts/bringup.sh), against test resources: a test repository, the test Matrix room, a budget-capped LiteLLM key; configuration in /root/nisse-e2e/.
  • Test repositories are made per run by the test operator (nisse-testing-operator, NISSE_OPERATOR_TOKEN), as an operator provides a project's: seeded from tests/integration/seed/, the agent a collaborator, main protected, a deploy key of its own; deleted afterwards (scripts/e2e-cleanup.sh for leftovers). They replaced the shared sandbox repository, whose state accumulated across runs.
  • A build VM for bring-up is provided by the operator by hand until Terraform (Phase 6); the agent reaches it over SSH with a key from /root/nisse-e2e/ssh/.

3. How we work

  • One PR per milestone, each starting with a short implementation plan per CLAUDE.md. A milestone marked needs discussion starts with a design discussion first.
  • Every change comes with tests, through scripts/check.sh.
  • The end-to-end test runs on every PR (M1.6): the real agent, every role on a local model (so it costs nothing per call), a repository of the run's own and a real build host, driven by a scripted operator. CI runs it as its own job on pull requests, cancelling a run a newer push supersedes. Locally only the tests being written (-k) or diagnosed (--lf); scripts/e2e.sh reports what a run spent. Manual live runs are for the new loop's first runs and phase ends. Findings are filed as issues and either fixed before moving on or deliberately deferred.
  • The Quint models move with the loop: orchestrator.qnt while control.py runs, loop.qnt for the new loop, whose properties become tests as each piece lands (Phase 2).
  • control.py gets fixes only, and only for what blocks a live run. New behaviour goes into the new loop.
  • Bring-up runs on this box as root, against test resources only, with today's gates on until the classifier and trust dial are proven (Phase 3).
  • This plan is revised as we go, in the same PR as the work that changes it.

4. Phases

Phase 0 — Housekeeping (done)

M0.1 Retire the old spec. Done. M0.2 A bring-up script. Done.

Phase 1 — Execution over SSH, and an end-to-end test

M1.1 Work items in the state store. Done.

M1.2 Transcript views. Done. (#78 confirmed live, and closed.)

M1.3 Execution over SSH. Pre-approved. Done (#93).

  • execute(host, command, *, secrets, stdin) as the only way to run anything; file tools over SSH; the host bound by the harness from the project (L13).
  • The workspace lives on the build VM: cloned there, with no token in its configuration; the push key handed to each push only (D4, #89).
  • Every secret handed out is redacted from tool output (L12).
  • Tests against a throwaway sshd container.
  • Acceptance: the existing executor and delegation tests pass over SSH; a live run of one milestone on the operator's build VM.
  • Also landed, from that run (bring-up run 3): the push credential as an HTTPS token or an SSH deploy key; flat harness branch names, after the executor made a branch named after the task; publishing only the work (#80), brought forward from M2.1; credentials kept out of every repr.

M1.6 The end-to-end test. Pre-approved. Done (#95): scripts/e2e.sh.

  • Automates bring-up run 3: the assembled agent, real models, the Gitea sandbox and a real build host, with a scripted operator that answers whatever the agent asks.
  • Asserts what was checked by hand: a PR on the sandbox containing only the work, pushed with the push credential; no credential in the clone; the planner's next turn citing the facts rather than the executor's turns.
  • Runs against the current loop now, and against the new loop from M2.1.

Phase 1 acceptance: the end-to-end test passes against the current loop. Done: it passes on the bring-up build VM.

Moved after M2.1: M1.4 (projects) and M1.5 (the container image). Neither is needed for a minimal loop running live; both are done before the switch-over (M2.8), when several projects and deployment start to matter.

Phase 2 — The new loop, as a thin slice first

Built alongside control.py, reusing the state store, log, views, publisher, pollers and recovery. The first milestone is the smallest end-to-end path; each later one widens it and extends the end-to-end test (M1.6) to cover it.

M2.1 The slice. Needs discussion (the loop's shape in code). Done (#96, #97, #98, #99; first live run: sandbox #255, follow-ups in #100).

  • An issue assigned to dev-agent → a work item (D1); a restatement in the item's thread; a go-ahead bound to its revision (L3, L5); one milestone through start_milestone / finish_milestone on a harness branch (D4); the PR; a review comment answered (D5); the merge; the item closed.
  • Includes what carries over: a fresh workspace at item start and harness-owned branches (D3, D4, #62); review intake, inline comments and the watch stall (#69, #70); the review-fix check after merge. (Publishing only the work, #80, landed early in M1.3.)
  • loop.qnt's properties for these paths become tests.
  • Acceptance: the end-to-end test runs that path on the new loop, plus a crash mid-publish; then a first manual live run.

M2.2 The queue. Pre-approved. Done (this PR). Several items: states, park-and-switch with branches pushed, next-item order, blocked items from Gitea dependencies, a closed PR handled (L1, D4). End-to-end: two issues and a dependency.

  • Switching happens as soon as the active item waits; the grace period (§6, L1) is left until a watching operator misses it. Order is "do #N next"; priority labels and driver-chosen order wait for a need.
  • The property walk covers several issues, dependencies and the operator's order, and checks that parked work is never lost (every file an open item wrote is on the workspace or in the forge).

M2.3 Threads and labels. Pre-approved. Done (this PR). Routing by thread, ambiguous commands asked about (L5); bug grace periods, discuss, design; questions and plain-language go-aheads (D1). End-to-end: a bug and a feature, labelled and not.

  • Commands naming their item ("abandon #14") apply to it anywhere; go, approve and abandon alone at top level are asked about. stop is never an answer.
  • A plain-language go-ahead is read by one model call (GoAheadReader, on the driver's model until the classifier role, M2.6); questions never reach it.
  • bug waits tuning.loop.bug_grace_s (default 10 minutes) after its restatement; any reply stops the countdown. discuss isn't offered restate until the operator has spoken; design is steered by the driver's instructions.
  • Labels are read at intake; a label changed later is not picked up yet.

M2.4 Multi-milestone work and documents. Pre-approved. Done (this PR). Build plans in the repository, ARCHITECTURE.md kept current, waiting for merges between milestones (D2, D4). End-to-end: a two-milestone feature.

  • Every milestone branch is cut from the latest default branch, so the next one builds on the merged previous and a redo drops a closed PR's work. While the item's PR is open, start_milestone is refused, the PR's state read from Gitea at that moment. finish_milestone(final): earlier PRs say "Part of #N", the last "Closes #N".
  • close_item with the item's PR still open waits for the merge.
  • Documents are the driver's instructions only; the harness never parses a plan.
  • Parking stashes uncommitted work and pushes it to <item>-parked, put back on resume, instead of committing it onto the item's branch: the walk found a half-done review fix parked onto a PR that had merged meanwhile, where it was lost.
  • Deferred: a milestone with no changes that wasn't expected to change code is still raised with the operator (D4).

M2.5 Conversations and new projects. Done (#106 and this PR). Needs discussion; the design was agreed in this PR (general scope, L1, L5; the new-project sequence, D1). Work started in conversation, record issues carrying their item's ID, the new-project flow and its project entry (D1, D8, #29). After M1.4. End-to-end: a small new project, in a repository the test operator creates under its own account for the run and deletes afterwards.

  • PR A, conversations — done (this PR).
    • A top-level message that isn't a command is a general item, threaded under it; the driver gets reply, ask_human and propose_work, with no workspace.
    • Agreed work (a go-ahead, or a plain yes, on the proposal) is filed under an intent as a record issue carrying the new item's ID. Its item starts agreed, with no second restatement. Intake skips any issue carrying an ID, and boot settles a filing cut off by a crash.
    • A conversation closes after tuning.loop.general_idle_s without a message; a reply in its thread then starts a new one that continues it.
  • PR B, new projects — done (this PR).
    • propose_project(name, purpose, decisions) goes up for a go-ahead.
    • On go, the checklist: repository, protection, collaborator, build VM, deploy key, and the project entry as YAML to fill in.
    • On "done", the agent reads its configuration again and adds the new project live (only additions). It then checks the access: the repository's permissions and protection as the agent sees them, then in practice on a throwaway branch with an empty commit (a branch push must succeed, a push to the default branch and merging its own PR must be refused); the branch and PR are removed. Anything that fails is said, and nothing starts.
    • When all is well: the tracking issue with the distilled decisions, and the project's item, agreed and labelled design, whose first milestone is ARCHITECTURE.md and the build plan. A conversation waiting on provisioning doesn't close as idle.

M2.6 Roles and capability profiles. Pre-approved. driver, helper, expert, classifier (L9); escalation triggers; delegation and ask_expert on the new loop.

M2.7 Conversation. Pre-approved. Explanations, progress in prose, asking mid-work (L5, #42, #77).

M1.4 Projects (D8). Pre-approved. Done (this PR).

  • The project entry in configuration: repository, default branch, build VM, label defaults, secrets by name with their visibility, egress additions.
  • Acceptance: the bring-up configuration is one project entry; a second project needs only a second entry.
  • projects: {name: entry}. The old loop runs exactly one project and refuses more. On the new loop each project has its own clone, workspace, push credential and milestones. Issues are named project#14 when two projects could both have #14, and a bare #14 that matches two is asked about. Switching projects parks the one worked on last.
  • Secrets are by ${VAR} reference only, commands or harness. commands secrets reach run_command as environment variables, redacted from output; harness secrets are held for later. Egress is recorded, not enforced (D7).
  • Deferred: config reload without a restart (with M2.5's entry step if wanted); the trust dial's configuration (M3.3).

M1.5 The agent as a container image. Pre-approved.

  • A Dockerfile for nisse-dev, stateless with a volume for state; a Gitea Actions workflow that builds it and pushes to Gitea's registry on each release tag (X4).
  • bringup.sh runs the image instead of a venv.
  • Acceptance: a tagged release produces an image; the end-to-end test runs from it.

M2.8 Switch over. Pre-approved, after acceptance. nisse-dev runs the new loop; control.py, its tests and orchestrator.qnt are removed.

Phase 3 — Authority

M3.1 Action classes and the fast path. Needs discussion. Harmless, contained and dangerous actions per agent (P3, D6), static fast-path rules.

M3.2 The classifier. Needs discussion. L4, its model, fail-closed verdicts, overrides as an evaluation set.

M3.3 The trust dial. Needs discussion. Per project (D8); agent merging behind protection it can't satisfy, verified by a test (D4, D5, #65).

Phase 4 — The environment

M4.1 Toolchain preflight, M4.2 recording installs, M4.3 environment repair. Pre-approved. All on the build VM (D3).

Phase 5 — Memory

M5.1 The vault. Pre-approved. The folder, per-agent mounts, control tools, atomic writes and provenance (L10).

M5.2 Agent memory (needs discussion) and M5.3 scope memory (pre-approved): when notes are written and read, verbatim corrections (L6).

M5.4 The operator's copy. Pre-approved. Syncthing, directions per folder.

Phase 6 — Production

M6.1 The agent host. Needs discussion. Containers, volumes, snapshots, per-agent networks (X1, X2, X4).

M6.2 Build VMs by Terraform. Needs discussion. The template, VLAN and egress (D7, X2), collection when idle.

M6.3 Secrets and identity. Pre-approved. Per-agent secret sets on the host, LLDAP principal (L12).

M6.4 Delivery. Pre-approved. Watchtower, restarts gated on an idle flag (X4).

M6.5 The browser tool. Pre-approved. On the internal test network (D7).

Phase 7 — nisse-core and nisse-ops

M7.1 Extract nisse-core. M7.2 MCP servers (#37). M7.3 Approved step sequences (O2). M7.4 Ops intake and duties from the infrastructure repository (O5). M7.5 The ops tool VM and deployment (O6). M7.6 Requests between agents: nisse-dev asking for build VMs (L1, O5). All needs discussion except M7.1.

Not yet scheduled

From the architecture's open questions and older issues: filing issues from conversation; stacked PRs; releases; nisse-ops issuing credentials; a server database; recovering the agent host (an ops issue); more than one active work item; vision; one local model for every agent; several forges (#26); a room per project (#28).


5. Open issues and where they land

Issue Lands in
#26 multiple forges Not yet scheduled
#27 per-project state, clone on use M1.3 (clone on the build VM), M1.4 (projects)
#28 room per project Not yet scheduled (threads, M2.3, may make it unnecessary)
#29 create a project from scratch M2.5 (ownership settled by D4, D8)
#37 MCP servers M7.2
#42 per-turn commentary M2.7
#62 branch at execution start M2.1
#65 agent merges approved PRs M3.3
#69 inline review comments M2.1
#70 watch stall M2.1
#77 conversational agent M2.3 (questions), M2.7

6. Implementation notes

Mechanism detail moved out of docs/Architecture.md in PR #90, which keeps only decisions and their reasons. Keyed by the architecture section each note implements; a milestone touching that section uses the note, and changes it here if the implementation differs.

  • L1 switching: the grace period before switching away from an item waiting on the operator defaults to 10 minutes. When the driver chooses the next ready item and the choice fails or is invalid, fall back to the oldest.
  • L3 revision stamping: in Matrix, a reply is stamped with the revision whose message had been sent when it arrived; on a Gitea issue, with the latest proposal comment older than the reply.
  • L5 transport: the Transport interface is send, ask and receive. Intake backoff is exponential, capped at a few minutes.
  • L6 fitting order: first shorten old tool results to their first and last lines, then drop the oldest events with a note saying so; never the system prompt, the current plan or the most recent turns. View labels: [orchestrator], [operator, Matrix], [operator, comment on PR #N], [helper report], [executor] narration.
  • L7 rendering: content is stored as bytes or local paths and uploaded or inlined at render time, never as provider handles. Token budgeting and prompt-cache breakpoints are render-time concerns, never stored. Compaction summaries are first-class events so a model change never inherits opaquely compacted history. A reasoning "session" is a delegation, including one resumed after a crash.
  • L8 state store: SQLite in WAL mode, each change committed and fsynced before the loop continues. A delegation's cut is clean when its last event is a completed result, its branch is at the expected commit, its caps are unbreached and external truth matches the log. "Anything else" offers continue, re-plan or abandon.
  • L9 local models: request tool_choice only of models whose server declares it can enforce it; otherwise the loop enforces the contract (an explicit finish, prose treated as a violation). Briefings use the capability profile, never a model name or "weaker model".
  • L10 vault: atomic writes are write-then-rename. Obsidian's settings folder (and .git, if history is kept) are not synced. A failed write is retried, or recorded and reconciled later.
  • L12: secrets reach a command by environment or stdin. Headless agents get an Authelia single-factor exception scoped by source address, group and target. Logs are shipped to the host journal, not kept in containers.
  • D3 preflight: a project's needs are read from its files (Cargo.toml, pyproject.toml, package.json) or a declaration in the repository.
  • D4 publishing: standard excludes are configured in each clone, and only what the work produced is committed. The push credential is handed to each push only: a deploy key over stdin to a short-lived ssh-agent on the build VM, or a push-only account's HTTPS token as that command's secrets, read by a credential helper that names environment variables, never values.
  • D7: test services use ports 18000–18099, so opening access later is a firewall change. The inference host is behind LiteLLM, so it is not a second egress exception.
  • X4: the agent host's state dataset is ZFS, snapshotted on a schedule and on each approval. Tool VM templates use Terraform's bpg/proxmox provider with cloud-init. Containers restart unless stopped.
  • X5: the local inference host is llama-swap on an RTX 4090 machine.