Nisse — Development Plan
Status: agreed (PR #84); reworked in PR #92 after the architecture revision (PR
#90). How to get from the code as it is to the architecture in
docs/Architecture.md, in what order, and how each step is accepted. The
architecture says what and why; this document says how and when, and is revised
as work lands.
The priority is a minimal new loop, running live. Work is ordered to reach the smallest end-to-end version of the conversational loop (M2.1) as soon as possible; everything not needed for it waits. Each milestone is checked by an automated end-to-end test against real resources, not by hand.
1. Where we are
A survey of main (2026-10-02) against the architecture. Done means it exists
and matches; partial, something exists but needs changing; none, not
started.
Only nisse-dev has real code; nisse-core and nisse-ops are placeholders.
| Section | Status | Notes |
|---|---|---|
| L1 Work model | mostly done | Work items with an active pointer (M1.1); issue intake (M2.1); queue, parking and blocked items (M2.2) on the new loop; no grace period yet |
| L2 Agent loop | mostly done | The loop (Phase 2), the only one since the switch-over (M2.8): driver runs, waits, stop, abandon, question runs |
| L3 Authority | partial | Go-aheads bound to the restatement's revision, on the issue and its conversation (M2.1); no action classes yet (M3.1) |
| L4 Classifier | none | |
| L5 Conversation | partial | Matrix transport, mentions, lenient commands; on the new loop, a thread per item, named and ambiguous commands, plain-language go-aheads (M2.3); little explanation |
| L6 Context | partial | Context fitting, per-role views and orchestrator facts (M1.2); no scope or agent memory |
| L7 Canonical log | partial | Work item and actor on every event, fact (M1.1, M1.2); no classifier_verdict, knowledge_retrieved |
| L8 Durability | mostly done | WAL store, intents, boot reconciliation, PR adoption, comment redelivery; to move onto the new loop |
| L9 Models and roles | mostly done | LiteLLM, eval capture; on the new loop: driver/helper/expert/classifier pinned per item, capability profiles in briefings, delegation and ask_expert with triggers (M2.6) |
| L10 Knowledge vault | none | |
| L11 Injection | partial | Operator allowlists on every channel; no classifier |
| L12 Secrets, logging | partial | Structured state-change log; secrets in .env; no per-operation handout or redaction |
| L13 Execution | none | Tools run locally in the agent's process. The token leaks into the clone (#89) |
| D1–D2 Workflow | partial | On the new loop: issue intake, restatement and go-ahead (M2.1), labels (M2.3); no documents in the repo |
| D3–D4 Workspace, git | partial | Idempotent publishing; no fresh workspace (#62), git add -A (#80) |
| D5 Review | partial | PR conversation comments only (#69), watch stall (#70) |
| D7–D8 Deployment, projects | partial | Runs from a venv as a systemd unit on this box; project entries in config (M1.4); egress not enforced |
| O, X | none | No container image yet |
specs/ |
done for now | loop.qnt (the architecture, #91); orchestrator.qnt went with control.py (M2.8) |
2. The environment today
- Supporting services (X5): Matrix, Gitea, LiteLLM, Vaultwarden, LLDAP with Authelia. The infrastructure repository exists in Gitea.
- Local inference: llama-swap on an RTX 4090 host (320 W cap). The benchmark
(PR #55) chose
qwen3.8-27bfor local work. - Models by role today: driver and helper
claude-opus-5-5, expertclaude-haiku-4-5.qwen3.8-27bhas had no role since the executor's went (M2.8); the driver benchmark measures where it fits. - Bring-up runs on this development VM (
scripts/bringup.sh), against test resources: a test repository, the test Matrix room, a budget-capped LiteLLM key; configuration in/root/nisse-e2e/. - Test repositories are made per run by the test operator
(
nisse-testing-operator,NISSE_OPERATOR_TOKEN), as an operator provides a project's: seeded fromtests/integration/seed/, the agent a collaborator,mainprotected, a deploy key of its own; deleted afterwards (scripts/e2e-cleanup.shfor leftovers). They replaced the shared sandbox repository, whose state accumulated across runs. - A build VM for bring-up is provided by the operator by hand until Terraform
(Phase 6); the agent reaches it over SSH with a key from
/root/nisse-e2e/ssh/.
3. How we work
- One PR per milestone, each starting with a short implementation plan per
CLAUDE.md. A milestone marked needs discussion starts with a design discussion first. - Every change comes with tests, through
scripts/check.sh. - Testing has three levels (M1.6): every PR runs the checks (unit tests across
the runner's cores, 16 property walks from a moving seed, integration) and the
end-to-end smoke tests; a PR labelled
e2e:full, a push tomainand a manual run add all 48 walks and the whole end-to-end suite; a published release runs that full set before its image is built. The end-to-end tests drive the real agent, every role on a local model (so they cost nothing per call), in a repository of the run's own, with a scripted operator; CI runs them after the checks pass. There is one runner, so a newer run for a PR or branch cancels the one it supersedes (#126). Locally only the tests being written (-k) or diagnosed (--lf);scripts/e2e.shreports what a run spent. Manual live runs are for the new loop's first runs and phase ends. Findings are filed as issues and either fixed before moving on or deliberately deferred. - The Quint model moves with the loop:
loop.qntmodels the architecture, and its properties are tests (the property walk), changed in the same PR as a rule they cover. - Bring-up runs on this box as root, against test resources only, with today's gates on until the classifier and trust dial are proven (Phase 3).
- This plan is revised as we go, in the same PR as the work that changes it.
4. Phases
Phase 0 — Housekeeping (done)
M0.1 Retire the old spec. Done. M0.2 A bring-up script. Done.
Phase 1 — Execution over SSH, and an end-to-end test
M1.1 Work items in the state store. Done.
M1.2 Transcript views. Done. (#78 confirmed live, and closed.)
M1.3 Execution over SSH. Pre-approved. Done (#93).
execute(host, command, *, secrets, stdin)as the only way to run anything; file tools over SSH; the host bound by the harness from the project (L13).- The workspace lives on the build VM: cloned there, with no token in its configuration; the push key handed to each push only (D4, #89).
- Every secret handed out is redacted from tool output (L12).
- Tests against a throwaway
sshdcontainer. - Acceptance: the existing executor and delegation tests pass over SSH; a live run of one milestone on the operator's build VM.
- Also landed, from that run (bring-up run 3): the push credential as an HTTPS token or an SSH deploy key; flat harness branch names, after the executor made a branch named after the task; publishing only the work (#80), brought forward from M2.1; credentials kept out of every repr.
M1.6 The end-to-end test. Pre-approved. Done (#95): scripts/e2e.sh.
- Automates bring-up run 3: the assembled agent, real models, the Gitea sandbox and a real build host, with a scripted operator that answers whatever the agent asks.
- Asserts what was checked by hand: a PR on the sandbox containing only the work, pushed with the push credential; no credential in the clone; the planner's next turn citing the facts rather than the executor's turns.
- Runs against the current loop now, and against the new loop from M2.1.
Phase 1 acceptance: the end-to-end test passes against the current loop. Done: it passes on the bring-up build VM.
Moved after M2.1: M1.4 (projects) and M1.5 (the container image). Neither is needed for a minimal loop running live; both are done before the switch-over (M2.8), when several projects and deployment start to matter.
Phase 2 — The new loop, as a thin slice first
Built alongside control.py, reusing the state store, log, views, publisher,
pollers and recovery. The first milestone is the smallest end-to-end path; each
later one widens it and extends the end-to-end test (M1.6) to cover it.
M2.1 The slice. Needs discussion (the loop's shape in code). Done (#96, #97, #98, #99; first live run: sandbox #255, follow-ups in #100).
- An issue assigned to
dev-agent→ a work item (D1); a restatement in the item's thread; a go-ahead bound to its revision (L3, L5); one milestone throughstart_milestone/finish_milestoneon a harness branch (D4); the PR; a review comment answered (D5); the merge; the item closed. - Includes what carries over: a fresh workspace at item start and harness-owned branches (D3, D4, #62); review intake, inline comments and the watch stall (#69, #70); the review-fix check after merge. (Publishing only the work, #80, landed early in M1.3.)
loop.qnt's properties for these paths become tests.- Acceptance: the end-to-end test runs that path on the new loop, plus a crash mid-publish; then a first manual live run.
M2.2 The queue. Pre-approved. Done (this PR). Several items: states, park-and-switch with branches pushed, next-item order, blocked items from Gitea dependencies, a closed PR handled (L1, D4). End-to-end: two issues and a dependency.
- Switching happens as soon as the active item waits; the grace period (§6, L1) is left until a watching operator misses it. Order is "do #N next"; priority labels and driver-chosen order wait for a need.
- The property walk covers several issues, dependencies and the operator's order, and checks that parked work is never lost (every file an open item wrote is on the workspace or in the forge).
M2.3 Threads and labels. Pre-approved. Done (this PR). Routing by thread,
ambiguous commands asked about (L5); bug grace periods, discuss, design;
questions and plain-language go-aheads (D1). End-to-end: a bug and a feature,
labelled and not.
- Commands naming their item ("abandon #14") apply to it anywhere;
go,approveandabandonalone at top level are asked about.stopis never an answer. - A plain-language go-ahead is read by one model call (
GoAheadReader, on the driver's model until the classifier role, M2.6); questions never reach it. bugwaitstuning.loop.bug_grace_s(default 10 minutes) after its restatement; any reply stops the countdown.discussisn't offeredrestateuntil the operator has spoken;designis steered by the driver's instructions.- Labels are read at intake; a label changed later is not picked up yet.
M2.4 Multi-milestone work and documents. Pre-approved. Done (this PR).
Build plans in the repository, ARCHITECTURE.md kept current, waiting for merges
between milestones (D2, D4). End-to-end: a two-milestone feature.
- Every milestone branch is cut from the latest default branch, so the next one
builds on the merged previous and a redo drops a closed PR's work. While the
item's PR is open,
start_milestoneis refused, the PR's state read from Gitea at that moment.finish_milestone(final): earlier PRs say "Part of #N", the last "Closes #N". close_itemwith the item's PR still open waits for the merge.- Documents are the driver's instructions only; the harness never parses a plan.
- Parking stashes uncommitted work and pushes it to
<item>-parked, put back on resume, instead of committing it onto the item's branch: the walk found a half-done review fix parked onto a PR that had merged meanwhile, where it was lost. - Deferred: a milestone with no changes that wasn't expected to change code is still raised with the operator (D4).
M2.5 Conversations and new projects. Done (#106 and this PR). Needs discussion; the design was agreed
in this PR (general scope, L1, L5; the new-project sequence, D1). Work started in
conversation, record issues carrying their item's ID, the new-project flow and its
project entry (D1, D8, #29). After M1.4. End-to-end: a small new project, in a
repository the test operator creates under its own account for the run and
deletes afterwards.
- PR A, conversations — done (this PR).
- A top-level message that isn't a command is a
generalitem, threaded under it; the driver getsreply,ask_humanandpropose_work, with no workspace. - Agreed work (a go-ahead, or a plain yes, on the proposal) is filed under an intent as a record issue carrying the new item's ID. Its item starts agreed, with no second restatement. Intake skips any issue carrying an ID, and boot settles a filing cut off by a crash.
- A conversation closes after
tuning.loop.general_idle_swithout a message; a reply in its thread then starts a new one that continues it.
- A top-level message that isn't a command is a
- PR B, new projects — done (this PR).
propose_project(name, purpose, decisions)goes up for a go-ahead.- On go, the checklist: repository, protection, collaborator, build VM, deploy key, and the project entry as YAML to fill in.
- On "done", the agent reads its configuration again and adds the new project live (only additions). It then checks the access: the repository's permissions and protection as the agent sees them, then in practice on a throwaway branch with an empty commit (a branch push must succeed, a push to the default branch and merging its own PR must be refused); the branch and PR are removed. Anything that fails is said, and nothing starts.
- When all is well: the tracking issue with the distilled decisions, and the
project's item, agreed and labelled
design, whose first milestone isARCHITECTURE.mdand the build plan. A conversation waiting on provisioning doesn't close as idle.
M2.6 Roles and capability profiles. Pre-approved. Done (this PR).
driver, helper, expert, classifier (L9); escalation triggers; delegation and
ask_expert on the new loop.
roles.driver(required since M2.8; until then, unset meant the planner's model) androles.classifier(unset: the expert's), pinned per item; the driver and the go-ahead reader run on the item's.profiles:in configuration (tools, strengths, weaknesses), used in briefings: the driver is told what its helper and expert are good at, the helper who will read its handback; never a model's name.delegate(task)andask_expert(question)for the driver. A helper works on a branch off the milestone's; its work comes back as uncommitted changes on a handback and is discarded otherwise, so harness branches never hold commits only the clone has (the walk found a fix stranded that way when a PR merged mid-help).- Triggers:
failure_limitfailed commands in a row, or the turn cap, mid- milestone, call a helper in once per milestone; if it fails too, the item waits on the operator as before. A delegation cut off by a crash is discarded at boot. - Evaluation capture: delegations,
ask_expertand the reader's verdicts. - Deferred: the context-won't-fit trigger (L6); the action classifier (M3.2).
M2.7 Conversation. Pre-approved. Done (this PR). Explanations, progress in prose, asking mid-work (L5, #42, #77).
- Questions never change state: a message ending in
?to a waiting project item is answered in a question run (replyand look-only tools), and the item goes back to the very wait it was in, so a restatement up stays up and a go binds to it. - A restatement gives its reasons and the main alternative; a revision says what
changed (
restate(changed), sent back without it). - Progress: the driver's and a helper's own words for a turn are posted, trimmed,
at most once a minute per item;
detailsshows the last tool calls. A message arriving mid-run is acknowledged at once. - Deferred: streaming (#42); the question property in
specs/loop.qnt(the walk checks it against the code).
M1.4 Projects (D8). Pre-approved. Done (this PR).
- The project entry in configuration: repository, default branch, build VM, label defaults, secrets by name with their visibility, egress additions.
- Acceptance: the bring-up configuration is one project entry; a second project needs only a second entry.
projects: {name: entry}. Each project has its own clone, workspace, push credential and milestones. Issues are namedproject#14when two projects could both have#14, and a bare#14that matches two is asked about. Switching projects parks the one worked on last.- Secrets are by
${VAR}reference only,commandsorharness.commandssecrets reachrun_commandas environment variables, redacted from output;harnesssecrets are held for later. Egress is recorded, not enforced (D7). - Deferred: config reload without a restart (with M2.5's entry step if wanted); the trust dial's configuration (M3.3).
M1.5 The agent as a container image. Pre-approved. Done (#115; accepted
2026-10-07: v0.1.0's published image passed the whole e2e suite, 9 of 9, run with
the release's own tests over it).
- A Dockerfile for
nisse-dev, stateless with a volume for state; a Gitea Actions workflow that builds it and pushes to Gitea's registry on each release tag (X4). bringup.shruns the image instead of a venv.- Acceptance: a tagged release produces an image; the end-to-end test runs from it.
- The image runs as its own user; state in
/var/lib/nisse-dev, configuration mounted at/etc/nisse-dev/nisse-dev.yaml, secrets as environment variables, keys mounted read-only. Itsteststage carries the tests over the installed package, forscripts/e2e.sh --image REF. Images are built only on release:release.ymlpushesgitea.dongar.net/dev/nisse-dev:<version>and:lateston a published release (REGISTRY_TOKEN, thedevorganization's). - Acceptance runs the tests over a published image:
docker build --target test --build-arg TEST_BASE=gitea.dongar.net/dev/nisse-dev:<version>from the release's checkout, thenscripts/e2e.sh --image; the test stage adds only the test tools, so the agent under test is the one published. - The live bring-up's switch to the image waits for the next live test (it needs
its own test repository too);
bringup.sh planshows what it will run.
M2.8 Switch over. Pre-approved, after acceptance. Done (this PR, after
the live session's fixes in #119 and #122). nisse-dev runs only the loop.
- Removed:
control.py,planner.py,executor.py,approvals.py,gates.py,publish.py,poller.py, the old assembly (agent.py, folded intoloop/build.py), the state store's state-machine view, their tests, the old end-to-end and live planning tests, andorchestrator.qntwith its scenarios. - Configuration:
loop:,roles.planner,roles.executorandtuning.executorare refused with what to use instead;roles.driveris required, andtuning.drivertakes the driver's turn cap and failure limit. - The benchmark and the capability matrix measure the driver: the loop's own
system prompt and tools, the task's plan as the agreed restatement. Task plans
end with
finish_milestone, so earlier runs show as(old). - A delegation on the loop records what its helper's alias resolved to (L9), as the old path's did.
Phase 3 — Authority
M3.1 Action classes and the fast path. Needs discussion. Harmless, contained and dangerous actions per agent (P3, D6), static fast-path rules.
M3.2 The classifier. Needs discussion. L4, its model, fail-closed verdicts, overrides as an evaluation set.
M3.3 The trust dial. Needs discussion. Per project (D8); agent merging behind protection it can't satisfy, verified by a test (D4, D5, #65).
Phase 4 — The environment
M4.1 Toolchain preflight, M4.2 recording installs, M4.3 environment repair. Pre-approved. All on the build VM (D3).
Phase 5 — Memory
M5.1 The vault. Pre-approved. The folder, per-agent mounts, control tools, atomic writes and provenance (L10).
M5.2 Agent memory (needs discussion) and M5.3 scope memory (pre-approved): when notes are written and read, verbatim corrections (L6).
M5.4 The operator's copy. Pre-approved. Syncthing, directions per folder.
Phase 6 — Production
M6.1 The agent host. Needs discussion. Containers, volumes, snapshots, per-agent networks (X1, X2, X4).
M6.2 Build VMs by Terraform. Needs discussion. The template, VLAN and egress (D7, X2), collection when idle.
M6.3 Secrets and identity. Pre-approved. Per-agent secret sets on the host, LLDAP principal (L12).
M6.4 Delivery. Pre-approved. Watchtower, restarts gated on an idle flag (X4).
M6.5 The browser tool. Pre-approved. On the internal test network (D7).
Phase 7 — nisse-core and nisse-ops
M7.1 Extract nisse-core. M7.2 MCP servers (#37). M7.3 Approved step
sequences (O2). M7.4 Ops intake and duties from the infrastructure
repository (O5). M7.5 The ops tool VM and deployment (O6). M7.6 Requests
between agents: nisse-dev asking for build VMs (L1, O5). All needs discussion
except M7.1.
Not yet scheduled
From the architecture's open questions and older issues: filing issues from
conversation; stacked PRs; releases; nisse-ops issuing credentials; a server
database; recovering the agent host (an ops issue); more than one active work item;
vision; one local model for every agent; several forges (#26); a room per project
(#28).
5. Open issues and where they land
| Issue | Lands in |
|---|---|
| #26 multiple forges | Not yet scheduled |
| #27 per-project state, clone on use | M1.3 (clone on the build VM), M1.4 (projects) |
| #28 room per project | Not yet scheduled (threads, M2.3, may make it unnecessary) |
| #29 create a project from scratch | M2.5 (ownership settled by D4, D8) |
| #37 MCP servers | M7.2 |
| #42 per-turn commentary | M2.7 |
| #62 branch at execution start | M2.1 |
| #65 agent merges approved PRs | M3.3 |
| #69 inline review comments | M2.1 |
| #70 watch stall | M2.1 |
| #77 conversational agent | M2.3 (questions), M2.7 |
6. Implementation notes
Mechanism detail moved out of docs/Architecture.md in PR #90, which keeps only
decisions and their reasons. Keyed by the architecture section each note
implements; a milestone touching that section uses the note, and changes it here
if the implementation differs.
- L1 switching: the grace period before switching away from an item waiting on the operator defaults to 10 minutes. When the driver chooses the next ready item and the choice fails or is invalid, fall back to the oldest.
- L3 revision stamping: in Matrix, a reply is stamped with the revision whose message had been sent when it arrived; on a Gitea issue, with the latest proposal comment older than the reply.
- L5 transport: the
Transportinterface is send, ask and receive. Intake backoff is exponential, capped at a few minutes. - L6 fitting order: first shorten old tool results to their first and last
lines, then drop the oldest events with a note saying so; never the system
prompt, the current plan or the most recent turns. View labels:
[orchestrator],[operator, Matrix],[operator, comment on PR #N],[helper report],[driver]narration. - L7 rendering: content is stored as bytes or local paths and uploaded or inlined at render time, never as provider handles. Token budgeting and prompt-cache breakpoints are render-time concerns, never stored. Compaction summaries are first-class events so a model change never inherits opaquely compacted history. A reasoning "session" is a delegation, including one resumed after a crash.
- L8 state store: SQLite in WAL mode, each change committed and fsynced before the loop continues. A delegation's cut is clean when its last event is a completed result, its branch is at the expected commit, its caps are unbreached and external truth matches the log. "Anything else" offers continue, re-plan or abandon.
- L9 local models: request
tool_choiceonly of models whose server declares it can enforce it; otherwise the loop enforces the contract (an explicitfinish, prose treated as a violation). Briefings use the capability profile, never a model name or "weaker model". - L10 vault: atomic writes are write-then-rename. Obsidian's settings folder
(and
.git, if history is kept) are not synced. A failed write is retried, or recorded and reconciled later. - L12: secrets reach a command by environment or stdin. Headless agents get an Authelia single-factor exception scoped by source address, group and target. Logs are shipped to the host journal, not kept in containers.
- D3 preflight: a project's needs are read from its files (
Cargo.toml,pyproject.toml,package.json) or a declaration in the repository. - D4 publishing: standard excludes are configured in each clone, and only what
the work produced is committed. The push credential is handed to each push
only: a deploy key over stdin to a short-lived
ssh-agenton the build VM, or a push-only account's HTTPS token as that command's secrets, read by a credential helper that names environment variables, never values. - D7: test services use ports 18000–18099, so opening access later is a firewall change. The inference host is behind LiteLLM, so it is not a second egress exception.
- X4: the agent host's state dataset is ZFS, snapshotted on a schedule and on
each approval. Tool VM templates use Terraform's